|
All outputs are fully variable and each test set has
a nominal duty cycle when delivering full current and voltage. Continuous
operation is possible at 40% of maximum current. Current and voltage
outputs are varied automatically from the controller. The output current
is supplied through wing nut terminals to the low inductance lead set
(available optionally).
The voltage output has a separate
pair of terminals. Each test set has a built-in timer which itself has
three modes of operation ‘Forward’, ‘Run-back’ and ‘Dual’. These enable
the function of a protective relay to be fully tested in regard to its
operating times. The timer may be stopped by the contacts of the
protection relay under test, or by the cessation of current flow or
manually by the operator. The timer stop inputs accept either unenergised
or a.c./d.c. energised relay contacts.
All current and voltage levels
are shown on the dot-matrix liquid crystal display incorporated in the
controller. The display also shows the elapsed time measured by the
counter. The equipment is microprocessor controlled and three tactile keys
on the control box take up the selected function allotted to them during
the testing programme. These functions are indicated on the display. The
display can be set to read in any of five languages, English, French,
German, Italian and Spanish.
Circuit protection is by circuit
breakers and fuses, and a thermal cut-out prevents overheating. Controlled
switching ensures that, in the event of power failure or the thermal
cut-out operating, the output cannot be re-energized until the
controls are reset, thereby offering protection to the equipment and the
operator.
Applications
Primary current injection test sets have two main applications.
The first of these is the testing of complete
relay protection systems comprising the isolated high voltage conductor,
the current transformer, the protection
relay and the circuit breaker. Because of the inconvenience of breaking
into the feeder circuit on the primary side of the current transformer,
primary current injection is normally applied at the time of commissioning
protection equipment or after major repair. Routine testing is carried out
using secondary current injection with
equipment such as the SCITS100 (100 A) or SCITS50D (50 A).
As many of the protection systems
requiring testing have a critical performance in relation to time, the
primary
current injection test sets incorporate a time counter facility. The
second role of the primary current injection test set is in the testing of
the current transformer in a protection system. Again, this test is
normally applied prior to commissioning equipment or after repair.
In addition to these protection
system applications, current injection test sets are ideal for any
application where it is necessary to supply a low resistance load with a
controlled and measured heavy current.
Primary Injection
Testing
Most electricity supply protective
equipment is fed from a current transformer on the supply cable or busbar.
Primary current injection testing checks all the components of the
protective system. A high test current, enough to cause the protection
equipment to operate, in injected into the supply cable. Time taken for
the protection relay to operate is then measured.
The primary current injection
test is essential when commissioning new protection systems and after
major repair and component replacement, since it tests the whole system.
It will detect current transformers
connected with incorrect polarity or relays that have been set in the
wrong sequence in differential systems.
However, the inconvenience of breaking the primary circuit means that the
method is unsuitable for routine
testing.
Secondary Injection
Testing
Secondary current injection testing
checks the operation of the protective relay etc. but does not test the
overall system including the current transformer. Primary testing usually
requires a high current (over 500 A). A secondary injection test is easier
since there is not the need to break the primary circuit and it requires a
lower current (up to 100 A) through the operating coil of the protective
device.
The time taken for the protection
device to operate is then measured. A test winding is sometimes provided
on the current transformer through which the secondary testing can be
carried out. |